Search
JOIN OUR NETWORK

     

     

 

 

« Areva loses a bundle in 2012 | Main | Areva moves to wind energy as nuclear continues to slide »
Wednesday
Dec052012

EPR: Four years behind, at least, and now even MORE over-budget

Source: CRILAN, an activist group in Normandy working to stop the EPR reactor at Flamanville and elsewhere and the construction of high-tension transmission line corridors. (CRILAN also serves as the global expert and watchdog on the La Hague reprocessing facility).

✔ 1.8 billion euros in 1998 when EdF envisaged building an EPR at Carnet, near Nantes, according to M. Ayrault. 

✔  3 billion euros in 2003, announced at a presentation in Rennes by the Minister of Industry.

✔  3.3 billion euros during the “Public Debate” organized after the decision to build the reactor on EDF land at Flamanville, from where the very long high-tension lines to reach the Loire Country, are also costly. 

✔ 6 billion euros in 2011 when, citing inside sources, CRILAN affirmed the the cost would be at least 8 billion euros. 

✔ Today, 8.5 billion euros! And the enormous cost over-run is not, as the company claims, only due to the make-good payments because of faulty subcontracting and post-Fukushima measures.   

How much in 2016 ? How much will we need to pay per kWh for electricity produced by this type of reactor? Three times more than anticipated? 

We still do not know, despite our repeated demands to the Local Commission on Information,what type of fuel will be used in the EPR! MOX, or more enriched uranium with cladding “doped” with chromium, or traditional uranium like at OLKILUITO ?