Estimates for new reactor construction costs continue to sky-rocket. Conservative estimates range between $6 and $12 billion per reactor but Standard & Poor's predicts a continued rise. The nuclear power industry is lobbying for heavy federal subsidization including unlimited loan guarantees but the Congressional Budget Office predicts the risk of default will be well over 50 percent, leaving taxpayers to foot the bill. Beyond Nuclear opposes taxpayer and ratepayer subsidies for the nuclear energy industry.

.................................................................................................................................................................................................................

Entries from May 1, 2012 - May 31, 2012

Saturday
May122012

More than $900 million cost overrun documented at Vogtle 3 & 4 new reactor construction project

"Burning Money" image by Gene Case, Avenging AngelsA coalition of environmental groups, including North Carolina Waste Awareness and Reduction Network (NC WARN), has issued a press release decrying a nearly billion dollar cost overrun at the Vogtle 3 & 4 new reactor construction project in Georgia. The groups warn that further cost increases are likely, due to rushed design and construction that has led to errors, as in sub-foundation grading, rebar quality assurance, and even radiological containment "shield building" design and construction.

The coalition's expert witness Arjun Makhijani, President of the Institute for Energy and Environmental Research (IEER), said: “Southern Company rushed into this project, as evidenced by the many requests for modifications of the license and early technical difficulties and problems including failure of ‘some details’ of early construction to conform to the Design Control Document, according to Georgia Power’s filing with the Securities and Exchange Commission.  Indeed, a part of the cost increase of $900 million appears to be attributable to overcoming delays and rushing the project again despite construction non-compliance.  The cost increase should not be a surprise; rather it is déjà vu all over again.  Rushing nuclear power reactors is not prudent and stockholders and/or the vendors, not ratepayers, should bear the burden of such costs.  It would be much better if construction were suspended until all design issues were resolved.”

Thursday
May102012

"Nuclear industry suffers major defeat in Iowa"

"Burning Money" image by Gene Case, Avenging AngelsFriends of the Earth (FOE) reports that the Iowa State Legislature has ended its session without approving "Construction Work in Progress" (CWIP), a gimmick by which nuclear utilities can charge ratepayers on their electricity bill for the construction of atomic reactors, even if they never recieve one watt of electricity from their involuntary "investment." The victory is thanks to the efforts of an environmental coalition, including FOE as well as grassroots groups such as Green State Solutions. The grassroots environmental victory comes despite intense lobbying efforts by Warren Buffett's MidAmerican Energy, which hoped to foist the construction costs for its proposed "dirty, dangerous, and expensive" atomic reactor onto the ratepayers of Iowa, despite 3/4ths of Iowans opposing the plan.