Search
JOIN OUR NETWORK

     

     

 

 

ARTICLE ARCHIVE

Safety

Nuclear safety is, of course, an oxymoron. Nuclear reactors are inherently dangerous, vulnerable to accident with the potential for catastrophic consequences to health and the environment if enough radioactivity escapes. The U.S. Nuclear Regulatory Commission, Congressionally-mandated to protect public safety, is a blatant lapdog bowing to the financial priorities of the nuclear industry.

.................................................................................................................................................................................................................

Saturday
Aug252012

FENOC weather seals severely cracked Davis-Besse shield building exterior -- 40 years too late

Painters work high off the ground to apply a protective weatherproof coating to Davis-Besse’s concrete Shield Building. Cracks were discovered in the fall that were blamed on the Blizzard of 1978. THE BLADE/AMY E. VOIGTAs reported by the Toledo Blade in an article entitled "Work crews apply waterproof coating to Davis-Besse: Project not silencing critics of plant," the only "corrective action" FirstEnergy Nuclear Operating Company (FENOC) plans to take, in response to severe cracking of its radiological containment "shield building," is to weather seal the exterior of the steel-reinforced concrete structure -- four decades too late. FENOC blames the cracking on the "brutal Blizzard of 1978,"which Beyond Nuclear has dubbed a snow job -- a charge repeated on the floor of the U.S. House of Representatives by long-time Davis-Besse watchdog, Congressman Dennis Kucinich (D-OH), whose constituents live immediately downwind and downstream from the problem-plagued plant. 

The article quoted both Terry Lodge, Toledo-based attorney representing the environmental coalition (Beyond Nuclear, Citizens Environment Alliance of Southwestern Ontario, Don't Waste Michigan, and the Green Party of Ohio) battling against Davis-Besse's 20-year license extension, as well as Beyond Nuclear's Kevin Kamps:

"I'm not at all comforted that they discovered an error that never should have happened to the most expensive and safety-significant building on the site," Mr. Lodge said Thursday.

Added Kevin Kamps of Beyond Nuclear, "It's 40 years too late. Weather sealant will not fix the cracks that are there."

As reported by Fox 8 Cleveland, a FENOC spokesman outright lied: “The shield building meets all its design parameters, we have evaluated it for all its parameters, and it is fully operable,” said Jon Hook, the design engineer manager at the plant.

In fact, both the U.S. Nuclear Regulatory Commission and FENOC itself have acknowledged that Davis-Besse's severe shield building cracking violates the atomic reactor's design and licensing bases. At an August 9th public meeting in Oak Harbor, OH, an NRC spokesman, with an audible scoff, admitted that NRC has generously granted FENOC until December 2012 to merely come up with a "plan for a plan" to "restore conformance" -- that is, pencil whip the violations, making everything appear okay on paper.  

Hook also told the Toledo Blade the shield building "wasn't coated originally because 'there was no requirement that it be done...'." Why such a basic no brainer as weather sealant was not required -- on the shoreline of Lake Erie, which suffers severe winter weather -- has never been explained, neither by FENOC nor NRC. Further deepening the mystery is the fact that all other -- much less safety significant and expensive -- concrete structures on site were weather sealed. When asked to explain, FENOC spokeswoman Jennifer Young has simply said it was done for aesthetic reasons, as those other structures appeared "splotchy." 

WNWO also reported on this story.

Monday
Aug202012

Greg Palast: "Fukushima: They Knew"

Investigative reporter Greg PalastFrom Shoreham nuclear power plant on Long Island, NY in 1986, to Fukushima Daiichi, Japan, in 2011, investigative reporter Greg Palast (photo left) documents that "they knew" that atomic reactor seismic qualifications were not up to real world risks. See Palast's article, "Fukushima: They Knew," here.

Friday
Aug172012

Kucinich weighs in on NRC OIG investigation of Ostendorff

U.S. Rep. Dennis Kucinich (D-OH)U.S. Representative Dennis Kucinich (D-OH) today weighed in on the U.S. Nuclear Regulatory Commission's (NRC) Office of Inspector General (OIG) investigation into whether or not NRC Commissioner William C. Ostendorff interfered with another OIG investigation, into why former NRC Chairman Gregory Jaczko was kept in the dark about radioactive and acidic water leaks, being caught in buckets in the control room of Entergy Nuclear's Palisades atomic reactor in Covert, Michigan. The Huffington Post broke that story yesterday.

Here is the text of Rep. Kucinich's press release:

Congressman Dennis Kucinich (D-OH) today issued the following statement concerning an investigation by the Inspector General of the Nuclear Regulatory Commission examining the possibility that a Nuclear Regulatory Commission (NRC) Commissioner undermined a probe of the Palisades [Nuclear] Power Plant in Michigan.

Yesterday, Congressman Kucinich requested the Inspector General investigate the agency’s public response to problems at Davis-Besse. Kucinich’s request came after the Nuclear Regulatory Commission held a hearing in Ohio to reassure the public about the safety of the plant. Official answers from NRC employees made at that hearing differed dramatically from what NRC engineers had previously told Kucinich and his staff.

“I can’t say the cases are related, but the similarities between these two investigations are troubling. In Michigan, an effort to determine why a radioactive leak was kept from the Chairman of NRC may have been undermined. In Ohio, we witnessed agency officials give public statements that varied dramatically from what engineers had told my staff. I cannot determine what caused this change in the answers of these Region III engineers, but I am concerned that it was in response to political pressure. I hope that the Inspector General is able to restore confidence in the NRC’s ability to provide effective oversight of our nation’s nuclear power plants,” said Kucinich.

Friday
Aug172012

Crack contention against Davis-Besse 20-year extension bolstered by NRC FOIA revelations

At the reactor's front gate, "Homer Simpson and Humpty Dumpty act out" FENOC's snow job "Blizzard of '78" theory for how/when/why Davis-Besse's concrete containment shield building cracked. The street theater was held in solidarity with the SAGE Alliance's March 24, 2012 day of action to shut down Vermont Yankee, and protested FENOC's Feb. 28th "root cause report."The environmental coalition challenging FirstEnergy Nuclear Operating Company's (FENOC) proposed 20-year license extension at the problem-plagued Davis-Besse atomic reactor, near Toledo on the Lake Erie shore, has bolstered its contention on the severe shield building cracking by citingU.S. Nuclear Regulatory Commission (NRC) documents revealed through a Freedom of Information Act (FOIA) request submitted by Beyond Nuclear. The coalition has issued a media release about its latest contention supplementation.

Toledo attorney Terry Lodge filed this FOIA supplement, the coalition's fifth this year, since filing the original contention on January 10th, just five days after the environmental intervenors confronted NRC and FENOC about the cracking at a special public meeting at Camp Perry, OH. The others include: (1) a Feb. 27th filing, based on U.S. Rep. Kucinich's (D-OH) revelation that the shield building's outer rebar layer was no longer structurally functional, due to the cracking; (2) a June 4th filing, in response to FENOC's woefully inadequate Aging Management Plan (AMP) for the shield building's cracks; (3) a July 16th filing, in response to FENOC's revised root cause analysis report, which revealed that shield building cracking was first observed not in October 2011, but rather August 1976; (4) a July 23rd filing, based on revelations in FENOC contractor Performance Improvement International's revised root cause assessment report, which revealed 27 areas of skeptical NRC questioning about FENOC's "Blizzard of 1978" theory of shield building cracking (the environmental Intervenors also posted documents supportive of its fourth supplement). The environmental coalition also defended its crack contention, on February 14th, against challenges by NRC staff and FENOC.

Beyond Nuclear has prepared a report, entitled "What Humpty Dumpty Doesn't Want You to Know: Davis-Besse's Cracked Containment Snow Job," which summarizes the coalition's work in 2012 on Davis-Besse's dangerously degraded condition.

Wednesday
Aug152012

Kucinich demands OIG investigation of NRC's two-faced "snow job" on Davis-Besse's cracked containment

U.S. Rep. Dennis Kucinich (D-OH), a long time watchdog on the problem-plagued Davis-Besse atomic reactorU.S. Representative Dennis Kucinich (D-OH, photo at left) has written to the U.S. Nuclear Regulatory Commission's (NRC) Office of Inspector General (OIG), demanding an investigation of NRC wrongdoing in regards to its Region 3 safety engineers telling him and his staff one thing months ago about Davis-Besse's shield building cracking, and another thing last Thursday night. Rep. Kucinich's office has issued a press release about his demand as well.

Kucinich referenced Beyond Nuclear's Freedom of Information Act (FOIA) request to NRC, which has revealed, among many other things, that NRC staff worked evenings, weekends, and even through the Thanksgiving holiday, in order to rush approval for FirstEnergy Nuclear Operating Company (FENOC) to restart Davis-Besse on December 2, 2011 -- despite not knowing the "root cause," extent, and safety and environmental risk significance of the cracking in the concrete shield building, nor what corrective actions needed to be made.

Kucinich joined with environmental coalition allies seeking to block Davis-Besse's proposed 20 year license extension at a press conference in the reactor's hometown of Oak Harbor, OH, 21 miles from Toledo on the Lake Erie shore, prior to a special NRC public meeting about the cracking scandal. Beyond Nuclear unveiled a new report, "What Humpty Dumpty Doesn't Want You to Know: Davis-Besse's Cracked Containment Snow Job," which summarizes NRC's FOIA revelations. The environmental coalition's Toledo-based attorney, Terry Lodge, will file a motion this week to introduce into the record of the NRC Atomic Safety (sic) and Licensing Board operations extension proceeding these FOIA revelations.