The U.S. Nuclear Regulatory Commission is mandated by Congress to ensure that the nuclear industry is safe. Instead, the NRC routinely puts the nuclear industry's financial needs ahead of public safety. Beyond Nuclear has called for Congressional investigation of this ineffective lapdog agency that needlessly gambles with American lives to protect nuclear industry profits.

.................................................................................................................................................................................................................

Wednesday
Mar072012

Update on defending Great Lakes against risky atomic reactors

Satellite photo of the Great Lakes: 20% of the planet's surface fresh water; drinking water supply for 40 million people in 8 U.S. states, 2 Canadian provinces, and a large number of Native American/First Nations; and lifeblood of one of the world's biggest regional economiesThree weeks ago, we reported on Beyond Nuclear's efforts, in conjunction with environmental coalitions and concerned citizens, to shut down two especially risky atomic reactors on the Great Lakes shorelines that have been generating a lot of controversy recently: Palisades in southwest Michigan, and Davis-Besse in northwest Ohio.

A lot has happened since. NRC was forced to admit that Palisades has the most embrittled reactor pressure vessel in the U.S. NRC's repeated regulatory rollbacks have put it at risk of fracturing like a hot glass under cold water due to Pressurized Thermal Shock. And thanks to revelations by Congressman Dennis Kucinich, we've contended that Davis-Besse's containment cracking is so severe that its outer layer of steel reinforcement rebar is no longer performing its safety function. We joined Congressman Kucinich in challenging Davis-Besse's root cause report, which blames the cracking on the Blizzard of 1978, as a "snow job of convenience." Read more.

Wednesday
Mar072012

"Living on Borrowed Time" & "U.S. Nuclear Power Safety One Year After Fukushima": UCS shines spotlight on 15 near-misses at U.S. reactors in 2011, examines Japan "lessons learned," or not, at NRC

David Lochbaum, Director of the Nuclear Safety Project at the Union of Concerned Scientists (UCS), recently published NRC and Nuclear Power Plant Safety in 2011: Living on Borrowed Time, describing 15 near-misses at U.S. atomic reactors in 2011 alone. Note that 4 near-misses took place at reactors belonging to one nuclear utility, Entergy: 2 near misses at Palisades in Michigan, and 2 at Pilgrim in Massachusetts. (Yet another near-miss occurred at Cooper in Nebraska, owned by Nebraska Public Power District, but with support services provided, yet again, by Entergy.)

The Thom Hartmann Show interviewed Dave Lochbaum about his report.

On March 7th, Lochbaum and Edwin Lyman, senior scientist at UCS's Global Security Program, released a report entitled U.S. Nuclear Power Safety One Year After Fukushima. Lochbaum and Lyman summarized their findings in a special published by CNN.

Friday
Mar022012

"Demonic" reality of Fukushima, versus absurdity of NRC

NRC file photo of Peach Bottom 2 & 3, PennsylvaniaWhile top level Japanese government officials admit that they feared a "demonic chain reactor" of atomic reactor meltdowns not only at Fukushima Daiichi, but also at Fukushima Daini and Tokai nuclear power plants, which would have led to an evacuation of Tokyo and perhaps its permanent loss, the U.S. Nuclear Regulatory Commission's SOARCA report absurdly claims that a reactor meltdown at the Fukushima Daiichi identically designed Peach Bottom Units 2 and 3 in Pennsylvania, surrounded by several other nuclear power plants, would cause few to no casualties. Read more.

Friday
Mar022012

Davis-Besse blames Blizzard of '78 for containment cracks, but critics charge that's merely a "snow job of convenience"

U.S. Rep. Dennis Kucinich (D-OH)The long awaited First Energy Nuclear Operating Company (FENOC) "root cause analysis" on extensive cracking of the Davis-Besse concrete containment shield building was published on Feb. 28th. Astoundingly, the nuclear utility blames a severe blizzard in January 1978, and the fact that it failed to apply weatherproofing to the exterior of its containment. Asked why FENOC and its predecessors had failed to apply sealant from 1971 (when the shield building was first constructed) and 2012, FENOC spokeswoman Jennifer Young said simply it had not been required. When asked why other safety-significant concrete structures on site had been sealed, Young said their concrete exteriors appeared splotchy, so a coating was applied for cosmetic purposes.

The Toledo Blade quoted U.S. Congressman Dennis Kucinich (D-OH, pictured left) and Don't Waste Michigan's Michael Keegan:

"Every homeowner knows you paint a house not just for decoration, but to protect it from the elements," Mr. Kucinich said, repeating his assertion that the plant should be shut down until the shield building's strength is thoroughly assessed.

And Michael Keegan, a representative of Don't Waste Michigan -- one of several anti-nuclear organizations fighting FirstEnergy's petition for a 20-year license renewal after Davis-Besse's initial operating permit expires in five years -- called the Blizzard of 1978 explanation a "snow job of convenience."

"While it may be true that the extreme weather damaged the concrete, what other assaults have occurred since that time?" he asked. "How is it that [FirstEnergy] can suggest that they'll seal it now, and the damage will be arrested? The damage goes down to the rebar and is structural."

Kucinich has long watchdogged Davis-Besse. His assertive questioning of FENOC and NRC, his revelations to the public, and his success at winning an NRC public meeting on Jan. 5th -- with the backing of NRC Chairman Greg Jaczko -- have been the main sources of information about the significance of the cracking since it was first revealed in October. Based on this information, Beyond Nuclear and Don't Waste Michigan, allied with Citizens Environment Alliance of Southwestern Ontario and the Green Party of Ohio, filed a cracked containment contention on Jan. 10th against Davis-Besse's proposed 20 year license extension, which it defended on Feb. 14th.

Kucinich's  Feb. 8th revelation that the outer steel reinforcement rebar of the concrete containment shield building is now considered no longer structurally functional due to the severe, extensive cracking led to the environmental coalition, represented by Toledo attorney Terry Lodge, filing a supplement to its contention on Feb. 27th.

The Port Clinton News Herald also reported on this story, and the Toledo Blade's Tom Henry editorialized:

"Even if the U.S. Nuclear Regulatory Commission accepts FirstEnergy Corp.'s explanation of the cracks in the outer containment shield of its Davis-Besse nuclear power plant, the agency must look more closely at the utility's request to extend the plant's operating license...

Whether or not Davis-Besse's cracks amount only to engineering artifacts, they suggest a larger problem with due diligence. The NRC should investigate concrete industry standards and codes to determine whether Davis-Besse complies with them. The commission also needs to review critically the plant's safety analysis report.

The NRC must drive home a point it has made to FirstEnergy before: Minimal compliance with nuclear industry standards is not good enough -- especially at a plant the utility wants to operate for another two decades."

Monday
Feb272012

Environmental coalition supplements Davis-Besse cracked containment contention: Rep. Kucinich reveals outer rebar no longer functional

U.S. Congressman Dennis Kucinich (D-OH) has long watchdogged the Davis-Besse atomic reactor near ToledoThe environmental coalition opposing the Davis-Besse atomic reactor's 20 year license extension (Beyond Nuclear, Citizens Environment Alliance of Southwestern Ontario, Don't Waste Michigan, and the Green Party of Ohio) has filed a supplement to its cracked containment contention. In a motion filed with the U.S. Nuclear Regulatory Commission's Atomic Safety and License Board (ASLB) today, the coalition cited a Feb. 8th revelation by the office of U.S. Representative Dennis Kucinich (D-OH, pictured at left), which broke the news to the public that the NRC considers the outer rebar steel reinforcement layer in the Davis-Besse atomic reactor to have lost its functional effectiveness due to the extensive cracking. Despite this, NRC approved Davis-Besse's restart in early December 2011. The ASLB plans oral pre-hearings near Davis-Besse in the weeks ahead on the cracked containment contention. A copy of today's filing, with the Kucinich Feb. 8th media release, as well as an NRC inspection report dated Jan. 31st, is posted here. The NRC inspection report provides further detail on structural cracking in the upper 20 feet of the containment building. The coalition published a media release on today's filing, posted here.