TVA will declare two unfinished Bellefonte reactors "surplus"

After withdrawing last Friday its license application for planned reactors 3 and 4 at its Bellefonte, AL site, TVA has now abandoned the two incomplete reactors there, Bellefonte 1 and 2.  The Tennessee Valley Authority has announced it will consider "declaring as surplus and entertaining the sale of the Bellefonte Nuclear Plant site." Bellefonte 1 and 2 began construction more than 40 years ago until the project was halted in 1988 after squandering $4.6 billion.  TVA also holds the record for the longest reactor construction time at Watts Bar 2, which, if the reactor is indeed started this summer, will have taken 43 years from start to finish.